Home » Projets » 2005 SEA-ME-WE 4

2005 SEA-ME-WE 4

Direct shore ends / Laying and burial of FO cable

Location : Mediterranean Sea
Client : Alcatel Submarine Networks

Length (km): 2,95
Water depth (m) : 12
Vessel : Pontoon
Burial system : Dredge pump (with divers)
Burial depth (m) : 0,8
Product : Fibre optic cable
Weight (kg/m) : 5
Diameter : 46 mm

Other projects

  • 2004 SIR BANIYAS

    Lay and burial of 2×9 km of 33kV power cable between Jebel Dhanna and SIR BANIYAS (mainland to Island)
    Burial system : TM03 (Trencher)
    Plus d’infos
  • 2021 Saint Nazaire OWF

    EPCI contract for the Saint-Nazaire OWF Inter-array Cables Procurement, Installation and protection
    Burial system :
    Plus d’infos
  • 2001 APOLLO UK SHORE END

    Cable lay and burial BUDE shore end (UK).
    Burial system : TJV04 (Jetting)
    Plus d’infos