2011 ORMONDE WINDFARM

Post Lay Inspection and Burial of 32 infield power cables.
Location : Ormonde Offshore Windfarm – Irish Sea
Client : VSMC-ORMONDE ENERGY
Length (km): 19.3
Water depth (m) : 21
Vessel : DP vessel
Burial system : ROVJET605 (jetting) 
Burial depth (m) : 2
Product : Power Cable
Weight (kg/m) : max 25
Diameter : max 139 mm