Home » Projets » 2001 ULYSSE

2001 ULYSSE

Recover of existing cable (5 km), simultaneous lay and burial work (ESV12), PLIB work of joints (MED 1 and diver pump).

Location : ENGLISH CHANNEL
Client : ULYSSES 1 South FO Cable (MCI WORLDCOM)

Length (km): 5,1
Water depth (m) : 35
Vessel : Barge
Burial system : MED1 (Dredge pump) – ESV12 (Plough)
Burial depth (m) : 2
Product : Fibre optic cable
Weight (kg/m) : 9,7
Diameter : 57 mm

Other projects

  • 2017 IFA 2000 CABLES REPAIR

    Repair of 4 power cables being part of the IFA 2000 link .
    Burial system : MED 1 (Dredge pump) + ROVJET806 (jetting)
    Plus d’infos
  • 2011 WACS

    FO cable separate and direct shore ends in Congo and Angola / PLIB / installation of mattresses with ROS
    Burial system : TJV05 – EBJ (jetting) – ROS (mattresses)
    Plus d’infos
  • 2011 WALNEY 1

    Post Lay Inspection and Burial of infield power cables
    Burial system : ROVJET605 (jetting)
    Plus d’infos