Laying of 43 km of power cable between mainland / platforms and platforms. Post burial of 22.5 km of cable. I-tube and Jtube pulling.
Location : Democratic Republic of the Congo – Congo
Client : PERENCO
Length (km): 43
Water depth (m) : 0 to 100
Vessel : Barge
Burial system : ROVJET 806 + EBJ : jetting
Burial depth (m) : 1
Product : Power Cable
Weight (kg/m) : 19
Diameter : 105 mm