Home » Projets » 2014 PERENCO RDC CONGO

2014 PERENCO RDC CONGO

Laying of 43 km of power cable between mainland / platforms and platforms. Post burial of 22.5 km of cable. I-tube and Jtube pulling.
Location : Democratic Republic of the Congo – Congo
Client : PERENCO
Length (km): 43
Water depth (m) : 0 to 100
Vessel : Barge
Burial system : ROVJET 806 + EBJ : jetting
Burial depth (m) : 1
Product : Power Cable
Weight (kg/m) : 19
Diameter : 105 mm

Other projects

  • 2011 ORMONDE WINDFARM

    Post Lay Inspection and Burial of 32 infield power cables.
    Burial system : ROVJET605 (jetting)
    Plus d’infos
  • 2025 NOY YEU NOIRMOUTIER WINDFARM

    EPCI contract for the supply, installation and protection of inter-wind turbine cables for the YEU NOIRMOUTIER offshore wind farm.
    Burial system :
    Plus d’infos
  • 2018 ASC Perth

    1 separate shore end. 10 km cable installation with laying and burial.  Installation of articulated pipes.
    Burial system : TO Mobile (jetting)
    Plus d’infos