Home » Projets » 2024 ZHONG NENG

2024 ZHONG NENG

Assistance to laying

Location: Taiwan
Customer: SEAWAY 7

Length (km): n/A
Water depth (m) :
Vessel: Seaway Phoenix
Beaching system: RN/A
Beaching depth (m): N/A
Product : Power cable
cable type: ø

Other projects

  • 2022 GRACE HOPPER

    Separate landing in a directional borehole. Simultaneous installation and beaming with mechanical trencher
    Burial system :
    Plus d’infos
  • 2022 2/AFRICA GENES

    2 x Direct landings in Genoa. Installation of shells and post-sinking. Installation of grounding system
    Burial system :
    Plus d’infos
  • 2001 ULYSSE

    Recover of existing cable (5 km), simultaneous lay and burial work (ESV12), PLIB work of joints (MED 1 and diver pump).
    Burial system : MED1 (Dredge pump) – ESV12 (Plough)
    Plus d’infos