Home » Projets » 2014 GÉOCEAN BÉNIN

2014 GÉOCEAN BÉNIN

Laying of 14km of power cable between mainland and a platform. Burial in shallow water from 8m to the beach.
Installation of articulated pipes.

Location : Bénin
Client : GEOCEAN

Length (km): 14 
Water depth (m) : 0 to 26
Vessel : Barge
Burial system : EBJ (jetting)
Burial depth (m) : 1.5
Product : Power cable
Weight (kg/m) : 30
Diameter : 108 mm

Other projects

  • 2019 SVERDRUP

    Post lay burial of 199 km of sismic fibre optic cables in Johan Sverdrup field
    Burial system : ROVJET 1206 (jetting)
    Plus d’infos
  • 1997 SOUTH KOREA

    Main land to Island / HVDC power cable extension with piggy-backed fibre optic cable
    Burial system : COPS (mattresses protection)
    Plus d’infos
  • 2013 ANHOLT

    Post Lay Inspection and Burial of 111 infield power cables
    Burial system : ROVJET806 (jetting)
    Plus d’infos