Home » Projets » 2001 CROSSING TAT 14

2001 CROSSING TAT 14

PLIB works on telecom FO cable crossings with RTE / NGC power cables

Location : ENGLISH CHANNEL / TAT 14 FO cable system
Client : KDD – SCS

Length (km): 4,3
Water depth (m) : 35
Vessel : DP Vessel
BS : MED1 (Crawler fitted with dredge pump)
Burial depth (m) : 0,4
Product : Fibre optic cable
Weight (kg/m) : 5,8
Diameter : 46 mm

Other projects

  • 2024 DOGGER BANK B

    Supply of trenching support services, including personnel and equipment on board a dedicated trenching support vessel (TSV), for the Dogger Bank offshore wind farm inter-turbine cable installation and protection project.
    Burial system :
    Plus d’infos
  • 2011 DELMA REPAIR

    Provision of submarine power cable repair assistance.
    Burial system : Dredge pump (with divers)
    Plus d’infos
  • 2000 FLAG ATLANTIC 1

    3 separate shore end installations as part of the FLAG Atlantic 1 telecommunication cable system.
    Burial system : MED1 (Jetting) and ESV11 (Plough)
    Plus d’infos