Home » Projets » 2001 CROSSING TAT 14

2001 CROSSING TAT 14

PLIB works on telecom FO cable crossings with RTE / NGC power cables

Location : ENGLISH CHANNEL / TAT 14 FO cable system
Client : KDD – SCS

Length (km): 4,3
Water depth (m) : 35
Vessel : DP Vessel
BS : MED1 (Crawler fitted with dredge pump)
Burial depth (m) : 0,4
Product : Fibre optic cable
Weight (kg/m) : 5,8
Diameter : 46 mm

Other projects

  • 2020 HAVHINGSTEN System

    Laying and burial of 1 fiber optic cable in Blackpool (UK) and 2 fiber optic cables in Houstrup (Denmark).
    Burial system : TO Mobile NV
    Plus d’infos
  • 2014 BUTENDIEK

    Provision of personnel and equipment to carry out the post burial of 86 infield power cables.
    Burial system : ROVJET806 (jetting)
    Plus d’infos
  • 2023 GHANA 2

    Recovery and replacement of damaged Ace cable in Accra. Laying and post-wiring of 5 km of fiber optic cable
    Burial system :
    Plus d’infos