Lay and burial of 2×9 km of 33kV power cable between Jebel Dhanna and SIR BANIYAS (mainland to Island)

Location : Sir Baniyas Island – UAE
Client : NEXANS NORWAY

Length (km): 18
Water depth (m) : 12
Vessel : Barge
Burial system : TM03 (Trencher)
Burial depth (m) : 1,2
Product : Power Cable
Weight (kg/m) : 27
Diameter : 135 mm