Home » Projets » 2003 AL KHAFJI

2003 AL KHAFJI

Cable laying and burial between mainland and platform.

Location : Saudi Arabia
Client : McDermott Arabia Company Ltd

Length (km): 40
Water depth (m) : 0-32
Vessel : DP vessel
Burial system : TM02 (trenching)
Burial depth (m) : 1,5 – 2
Product : Power Cable
Weight (kg/m) : 54
Diameter (mm) : 146

 

Other projects

  • 2021 AMITIE

    Separate shore ends in La Grigne. HDD Pulling, Laying and burial of 2.3 km of fibre optic cable.
    Burial system :
    Plus d’infos
  • 2007 ATLAS OFFSHORE

    FO cable shore ends – Post lay burial
    Burial system : EBJ 04 (jetting)
    Plus d’infos
  • 2025 CSN-1 COLOMBIA

    Separate landing in Barranquilla. Laying and post-wiring of 8.5 km of fiber optic cable, Installation of grounding system
    Burial system :
    Plus d’infos