Home » Projets » 2017 QUINTILLION ALASKA

2017 QUINTILLION ALASKA

1 separate shore end. 16 km cable installation with laying and burial.

Location : Prudhoe Bay/ Alaska
Client : Alcatel-Lucent Submarine Networks Ltd

Product : Fibre optic cable 
Length (km): 16
Water depth (m) : up to 15 m
Vessel : Barge
Burial system : ESV12 (Vibrating plough)
Burial depth (m) : 2
Weight (kg/m) : 4
Diameter (mm) : 37.5

Other projects

  • 2023 MARTINIQUE

    Installation of 2 new electrical links in the bay of Fort de France
    Burial system :
    Plus d’infos
  • 2005 ORASCOM MED CABLE

    MED CABLE direct shore ends (FO)
    Burial system : TJV07 (Jetting)
    Plus d’infos
  • 2018 ASC Indonesia

    Post lay inspection and burial of 41 km of fibre optic cable.
    Burial system : ROVJET 605 (jetting)
    Plus d’infos