Home » Projets » 2003 AL KHAFJI

2003 AL KHAFJI

Cable laying and burial between mainland and platform.

Location : Saudi Arabia
Client : McDermott Arabia Company Ltd

Length (km): 40
Water depth (m) : 0-32
Vessel : DP vessel
Burial system : TM02 (trenching)
Burial depth (m) : 1,5 – 2
Product : Power Cable
Weight (kg/m) : 54
Diameter (mm) : 146

 

Other projects

  • 2024 NIGERIA

    Separate landing in Lagos. 2.8 km of fibre-optic cable sunk in water
    Burial system :
    Plus d’infos
  • 2018 MERKUR OWF

    Provision of personnel and equipment to carry out the post lay burial of 57 infield power cables.
    Burial system : ROVJET 1210 (jetting)
    Plus d’infos
  • 2016 NORDSEE ONE

    Provision of personnel and equipment to carry out the post lay burial of 54 infield power cables.
    Burial system : ROVJET 810 (jetting)
    Plus d’infos