Home » Projets » 2003 AL KHAFJI

2003 AL KHAFJI

Cable laying and burial between mainland and platform.

Location : Saudi Arabia
Client : McDermott Arabia Company Ltd

Length (km): 40
Water depth (m) : 0-32
Vessel : DP vessel
Burial system : TM02 (trenching)
Burial depth (m) : 1,5 – 2
Product : Power Cable
Weight (kg/m) : 54
Diameter (mm) : 146

 

Other projects

  • 2022 2 AFRICA SOUTH AFRICA

    1 x Direct landing at Duynfontein, shell installation and post-burial. Installation of grounding system
    Burial system :
    Plus d’infos
  • 2006 THAILAND KHO SAMUI

    Shore ends/Mainland to island/Laying and burial of 115 kV power cable
    Burial system : TJV05 – TJV08 (Jetting)
    Plus d’infos
  • 2005 SEA-ME-WE 4

    Direct shore ends / Laying and burial of FO cable
    Burial system : Dredge pump (with divers)
    Plus d’infos