Home » Projets » 2014 PERENCO RDC CONGO

2014 PERENCO RDC CONGO

Laying of 43 km of power cable between mainland / platforms and platforms. Post burial of 22.5 km of cable. I-tube and Jtube pulling.
Location : Democratic Republic of the Congo – Congo
Client : PERENCO
Length (km): 43
Water depth (m) : 0 to 100
Vessel : Barge
Burial system : ROVJET 806 + EBJ : jetting
Burial depth (m) : 1
Product : Power Cable
Weight (kg/m) : 19
Diameter : 105 mm

Other projects

  • 2022 2 AFRICA MARSEILLE

    2 x Direct landing in Marseilles. Shell installation
    Burial system :
    Plus d’infos
  • 2019 SAFANIYA 6

    Provision of personnel and equipment to carry out the trenching of 11 submarine cables, umbilicals and flexibles on Safaniya 6 field.
    Burial system : TM03 (trencher)
    Plus d’infos
  • 2023 ZAKYNTIS

    LD Travocean was subcontracted by Asso Subsea for trenching work. ROVJET 1217 was deployed on the TSV MV Astrea to carry out PLB water jet cleaning on the 21 km electrical interconnection.
    Burial system :
    Plus d’infos