Home » Projets » 2014 PERENCO RDC CONGO

2014 PERENCO RDC CONGO

Laying of 43 km of power cable between mainland / platforms and platforms. Post burial of 22.5 km of cable. I-tube and Jtube pulling.
Location : Democratic Republic of the Congo – Congo
Client : PERENCO
Length (km): 43
Water depth (m) : 0 to 100
Vessel : Barge
Burial system : ROVJET 806 + EBJ : jetting
Burial depth (m) : 1
Product : Power Cable
Weight (kg/m) : 19
Diameter : 105 mm

Other projects

  • 2018 ASC Perth

    1 separate shore end. 10 km cable installation with laying and burial.  Installation of articulated pipes.
    Burial system : TO Mobile (jetting)
    Plus d’infos
  • 2024 HAI LONG

    Post Lay Burial of EXP
    Burial system :
    Plus d’infos
  • 1997 SOUTH KOREA

    Main land to Island / HVDC power cable extension with piggy-backed fibre optic cable
    Burial system : COPS (mattresses protection)
    Plus d’infos