2014 SAFANIYA 2

Provision of personnel and equipment to carry out the trenching of a 115 kV power composite cable in shallow water.

Location : SAFANIYA 2 oild field – Saudi Arabia
Client : Mc Dermott / Saudi Aramco

Product : Power Composite Cable
Length (km): 7.4
Water depth (m) : 0 to 7.5
Vessel : Barge
Burial system : TM03 (trenching)
Burial depth (m) : 1
Weight (kg/m) : 52
Diameter : 214 mm

Other projects

  • 2003 IFA 2000 – CABLE 11 REPAIR

    500 MW HVDC Power cable repair.
    Burial system : MED1 (Dredge pump)
    Plus d’infos
  • 2017 LTAII

    Provision of personnel and equipment to carry out trebsching services on a total of 10 submarine power cables.
    Burial system : TM03 + TM04 (trenchers)
    Plus d’infos
  • 2015 AMRUMBANK

    Provision of personnel and equipment to carry out the post burial of 86 infield power cables.
    Burial system : ROVJET810 (jetting)
    Plus d’infos