Home » Projets » 2018 ASC Perth

2018 ASC Perth

1 separate shore end. 10 km cable installation with laying and burial.  Installation of articulated pipes.

Location : Perth / Australia
Client : Alcatel-Lucent Submarine Networks Ltd

Product : Fibre optic cable 
Length (km): 10
Water depth (m) : up to 25 m
Vessel : Barge
Burial system : TO Mobile (jetting)
Burial depth (m) : 1
Weight (kg/m) : 2.8
Diameter (mm) : 37.5

Other projects

  • 2024 MARSEILLE

    1 x Direct landing in Marseille, installation of shells, post-sinking, installation of posidonia anchors. Installation of grounding system
    Burial system :
    Plus d’infos
  • 2014 GÉOCEAN BÉNIN

    Laying of 14km of power cable between mainland and a platform. Burial in shallow water from 8m to the beach.
    Burial system : EBJ (jetting)
    Plus d’infos
  • 2011 ORMONDE WINDFARM

    Post Lay Inspection and Burial of 32 infield power cables.
    Burial system : ROVJET605 (jetting)
    Plus d’infos