Home » Projets » 2018 ASC Perth

2018 ASC Perth

1 separate shore end. 10 km cable installation with laying and burial.  Installation of articulated pipes.

Location : Perth / Australia
Client : Alcatel-Lucent Submarine Networks Ltd

Product : Fibre optic cable 
Length (km): 10
Water depth (m) : up to 25 m
Vessel : Barge
Burial system : TO Mobile (jetting)
Burial depth (m) : 1
Weight (kg/m) : 2.8
Diameter (mm) : 37.5

Other projects

  • 2016 MARJAN GOSP

    Provision of personnel and equipment to carry out the post-lay burial of one 115 kV power cable.
    Burial system : TM03 (trenching)
    Plus d’infos
  • 2009 KASHAGAN

    Provison of burial services for 1 power cable and 2 umbilicals.
    Burial system : TM03 (Trencher)
    Plus d’infos
  • 2023 YUNLIN

    Assistance to laying
    Burial system :
    Plus d’infos