Home » Projets » 2021 HORNSEA 2

2021 HORNSEA 2

Provision of personnel and equipment to carry out the post lay burial of infield array cables.
Place: Hornsea 2 OWF UK waters

Client : Seaway 7
Product : Powercable
Length (km): 366
Water depth (m) : up to 50 m
Vessel : DP Vessel
Burial system : TM05 (trenching)+ROVJET1612 (jetting)
Burial depth (m) : 1.5

Period: May 2021 – May 2022

Other projects

  • 2015 ABU ALI

    Provision of personnel and equipment to carry out the post lay trenching of a 15 kV power composite cable.
    Burial system : TM03 (trenching)
    Plus d’infos
  • 2021 YUNLIN OWF

    Provision of personnel and equipment to carry out the post lay burial of infield array cables.
    Burial system :
    Plus d’infos
  • 2015 BALTIC 2

    Provision of personnel and equipment to carry out the post burial of 75 infield power cables.
    Burial system : ROVJET806 (jetting)
    Plus d’infos