Home » Projets » 2021 YUNLIN OWF

2021 YUNLIN OWF

Provision of personnel and equipment to carry out the post lay burial of infield array cables.

Place: YUNLIN OWF Taiwan
Client : Seaway 7

Product : Powercable
Length (km): 14
Water depth (m) :up to 50 m
Vessel : DP Vessel
Burial system :ROVJET1206 (jetting)
Burial depth (m) : 1.5

Period: July-nov 2021

Other projects

  • 2001 I 2 I / Shore end MADRAS

    Cable lay and burial – 8 km CHENNAI shore end.
    Burial system : TJV05 + TJV04 (Jetting) + ESV07 (Plough)
    Plus d’infos
  • 2015 ILE D’YEU

    Surface laying of 2 sections of power cable YEU3 and YEU4.
    Burial system : N.A.
    Plus d’infos
  • 2016 VEJA MATE

    Provision of personnel and equipment to carry out the post lay burial of 73 infield power cables.
    Burial system : ROVJET 810 (jetting)
    Plus d’infos