Home » Projets » 2021 HORNSEA 2

2021 HORNSEA 2

Provision of personnel and equipment to carry out the post lay burial of infield array cables.
Place: Hornsea 2 OWF UK waters

Client : Seaway 7
Product : Powercable
Length (km): 366
Water depth (m) : up to 50 m
Vessel : DP Vessel
Burial system : TM05 (trenching)+ROVJET1612 (jetting)
Burial depth (m) : 1.5

Period: May 2021 – May 2022

Other projects

  • 2000 PEC / LEVEL 3/ FLUTE

    PLIB works on telecom fibre optic cable crossings.
    Burial system : MED 1: Dredge pump / jetting tool
    Plus d’infos
  • 2011 DELMA REPAIR

    Provision of submarine power cable repair assistance.
    Burial system : Dredge pump (with divers)
    Plus d’infos
  • 2017 LTAII

    Provision of personnel and equipment to carry out trebsching services on a total of 10 submarine power cables.
    Burial system : TM03 + TM04 (trenchers)
    Plus d’infos