Provision of personnel and equipment to carry out the post lay burial of infield array cables.
Place: Hornsea 2 OWF UK waters

Client : Seaway 7
Product : Powercable
Length (km): 366
Water depth (m) : up to 50 m
Vessel : DP Vessel
Burial system : TM05 (trenching)+ROVJET1612 (jetting)
Burial depth (m) : 1.5

Period: May 2021 – May 2022

Other projects

  • 2007 PICOT / GONDWANA

    FO cable shore ends – Post lay burial
    Burial system : EBJ 04 (jetting)
    Plus d’infos
  • 2022 HORNSEA 2

    Assistance to laying, PLIB
    Burial system :
    Plus d’infos
  • 2004 SIR BANIYAS

    Lay and burial of 2×9 km of 33kV power cable between Jebel Dhanna and SIR BANIYAS (mainland to Island)
    Burial system : TM03 (Trencher)
    Plus d’infos