Home » Projets » 2023 CONGO

2023 CONGO

Separate landing at Pointe Noire. Laying and post-wiring of 8.8 km of fiber optic cable

Location: Pointe Noire – CONGO
Customer : ALCATEL SUBMARINE NETWORKS

Length (km): 8.8 km
Water depth (m) :
Vessel: NORA B
Beam system: TO MOBILE / NV
Beam depth (m): 2.0 m
Product : Fiber optic cable
cable type: ø37mm

Other projects

  • 2024 HAI LONG

    Post Lay Burial of EXP
    Burial system :
    Plus d’infos
  • 2024 MAJAN 1

    1 x Direct landing in Salalah, shell installation, post-sinking. Installation of grounding system
    Burial system :
    Plus d’infos
  • 2013 LONDON ARRAY

    Provision of personnel and equipment to carry out the post burial of 54 infield cables, some in very shallow water.
    Burial system : ROVJET605 (jetting)
    Plus d’infos