Home » Projets » 1996 THAILANDE

1996 THAILANDE

Mainland to KO SAMUI Island /Laying and burial of 115 kV power cable

Location : THAILAND / MAIN LAND to KO SAMUI
Client : ALCATEL / PEA

Length (km): 24
Water depth (m) : 26
Vessel : Barge
Burial system : TM02 (Trencher) – TJV04 (Jetting)
BD (m) : 1,5
Product : Power cable
Weight (kg/m) : 46
Diameter : 135 mm