Home » Projets » 2001 CROSSING TAT 14

2001 CROSSING TAT 14

PLIB works on telecom FO cable crossings with RTE / NGC power cables

Location : ENGLISH CHANNEL / TAT 14 FO cable system
Client : KDD – SCS

Length (km): 4,3
Water depth (m) : 35
Vessel : DP Vessel
BS : MED1 (Crawler fitted with dredge pump)
Burial depth (m) : 0,4
Product : Fibre optic cable
Weight (kg/m) : 5,8
Diameter : 46 mm

Other projects

  • 1998-1999 VNF PARIS

    Along river / Laying and burial of 3 multiple FO cables laid in one go
    Burial system : ESV 07 / ESV11 (Plough)
    Plus d’infos
  • 2022 EQUIANO

    1 x Direct landing at Sesimbra, shell installation and post-burial.
    Burial system :
    Plus d’infos
  • 2016 BBG FUJAIRAH

    1 direct FO shore-end in Fujairah (UAE). Protection of cable (burial and articulated pipes)
    Burial system : EBJ (jetting)
    Plus d’infos