Home » Projets » 2001 ULYSSE

2001 ULYSSE

Recover of existing cable (5 km), simultaneous lay and burial work (ESV12), PLIB work of joints (MED 1 and diver pump).

Location : ENGLISH CHANNEL
Client : ULYSSES 1 South FO Cable (MCI WORLDCOM)

Length (km): 5,1
Water depth (m) : 35
Vessel : Barge
Burial system : MED1 (Dredge pump) – ESV12 (Plough)
Burial depth (m) : 2
Product : Fibre optic cable
Weight (kg/m) : 9,7
Diameter : 57 mm