Home » Projets » 2010 HONOTUA

2010 HONOTUA

FO cable shore ends, PLIB and installation of articulated pipes.

Location : Bora Bora, Huaihina, Raiatea, Moorea, Papenoo
Client : ASN

Length (km): 3
Water depth (m) : 30
Vessel : N.A.
Burial system : Dredge pump (with divers)
Burial depth (m) : 0.2
Product : Fibre optic cable
Weight (kg/m) : 3,9
Diameter : 38 mm

Other projects

  • 2000 PEC / LEVEL 3/ FLUTE

    PLIB works on telecom fibre optic cable crossings.
    Burial system : MED 1: Dredge pump / jetting tool
    Plus d’infos
  • 2018 TRIANEL BORKUM II OWF

    Provision of personnel and equipment to carry out the post lay burial of 18 infield power cables.
    Burial system : ROVJET 1210 (jetting)
    Plus d’infos
  • 1999 DCN TOULON

    Power and composite cables inside miltary harbour.
    Burial system : N.A.
    Plus d’infos