Home » Projets » 2011 ORMONDE WINDFARM

2011 ORMONDE WINDFARM

Post Lay Inspection and Burial of 32 infield power cables.
Location : Ormonde Offshore Windfarm – Irish Sea
Client : VSMC-ORMONDE ENERGY
Length (km): 19.3
Water depth (m) : 21
Vessel : DP vessel
Burial system : ROVJET605 (jetting) 
Burial depth (m) : 2
Product : Power Cable
Weight (kg/m) : max 25
Diameter : max 139 mm

Other projects

  • 2001 I 2 I / Shore end MADRAS

    Cable lay and burial – 8 km CHENNAI shore end.
    Burial system : TJV05 + TJV04 (Jetting) + ESV07 (Plough)
    Plus d’infos
  • 2023 YUNLIN

    Assistance to laying
    Burial system :
    Plus d’infos
  • 2022 2 AFRICA & BLUE

    Pre Lay Grapnel Run (PLGR) & Route Clearance (RC) for the BLUE and 2Africa projects in the Mediterranean Sea
    Burial system :
    Plus d’infos