Home » Projets » 2022 2 AFRICA & BLUE

2022 2 AFRICA & BLUE

Pre Lay Grapnel Run (PLGR) & Route Clearance (RC) for the BLUE and 2Africa projects in the Mediterranean Sea

Location: Marseille France, Digue du large
Customer: ALCATEL SUBMARINE NETWORKS

Length (km): N/A
Water depth (m) :
Vessel: N/A
Trenching system: N/A
Trenching depth (m): N/A
Product:
cable type:

Other projects

  • 2025 CSN-1 PANAMA

    Separate landing at Costa del Este. Laying and post-wiring of 11.8 km of fiber optic cable
    Burial system :
    Plus d’infos
  • 2001 ULYSSE

    Recover of existing cable (5 km), simultaneous lay and burial work (ESV12), PLIB work of joints (MED 1 and diver pump).
    Burial system : MED1 (Dredge pump) – ESV12 (Plough)
    Plus d’infos
  • 2015 WASIT

    Provision of personnel and equipment to carry out the post lay trenching of a 15 kV power composite cable.
    Burial system : TM04 (trenching)
    Plus d’infos