Home » Projets » 2015 ABU ALI

2015 ABU ALI

Provision of personnel and equipment to carry out the trenching of 2 x 230 kV power cables in shallow water.

Location : Abu Ali – Saudi Arabia
Client : Mc Dermott Arabia Company Ltd

Product : Power Cable
Length (km): 2 x 5.9 km
Water depth (m) : 0 to 11
Vessel : Barge
Burial system : TM03 (trenching)
Burial depth (m) : 1.3
Weight (kg/m) : 96
Diameter : 237 mm

Other projects

  • 2021 EAUFON

    Separate shore ends in Chisasibi river. Laying and burial of 19 km of fibre optic cable. Installation of articulated pipes .
    Burial system :
    Plus d’infos
  • 2011 ORMONDE WINDFARM

    Post Lay Inspection and Burial of 32 infield power cables.
    Burial system : ROVJET605 (jetting)
    Plus d’infos
  • 2022 GRACE HOPPER

    Separate landing in a directional borehole. Simultaneous installation and beaming with mechanical trencher
    Burial system :
    Plus d’infos