Home » Projets » 2001 ANTARES

2001 ANTARES

Cable lay between LA SEYNE SUR MER and the Neutrinos Telescope ANTARES (max. depth 2400 m).

Location : FRANCE
Client : LA SEYNE SUR MER (ALCATEL SUBMARINE NETWORKS)

Length (km): 41,5
Water depth (m) : 2400
Vessel : DP Vessel
Burial system : N.A.
Burial depth (m) : 1
Product : Fibre optic cable
Weight (kg/m) : 9,7
Diameter : 21,5 to 57,7 mm

Other projects

  • 2023 ZAKYNTIS

    LD Travocean was subcontracted by Asso Subsea for trenching work. ROVJET 1217 was deployed on the TSV MV Astrea to carry out PLB water jet cleaning on the 21 km electrical interconnection.
    Burial system :
    Plus d’infos
  • 1999 ELGIN FRANKLIN

    Platform to platform / Composite power and communication cable + 1 composite power / communication cable + 1 umbilical.
    Burial system : CASTOR 2 (Trencher)
    Plus d’infos
  • 2023 BLUE GENOA

    2 x Direct landings at Genoa in a directional borehole. Shell installation
    Burial system :
    Plus d’infos