Home » Projets » 2006 THAILAND KHO SAMUI

2006 THAILAND KHO SAMUI

Shore ends/Mainland to island/Laying and burial of 115 kV power cable

Location : Gulf of Thailand
Client : NEXANS NORWAY

Length (km): 24
Water depth (m) : 28
Vessel : Barge
Burial system : TJV05 + TJV08 : Jetting
Burial depth (m) : 1,5
Product : Power Cable
Weight (kg/m) : 52
Diameter : 169 mm