Home » Projets » 2011 WALNEY 1

2011 WALNEY 1

Post Lay Inspection and Burial of infield power cables

Location : Walney Offshore Windfarm – Irish Sea
Client : VSMC-DONG

Length (km): 40
Water depth (m) : 20
Vessel : DP vessel
Burial system : ROVJET605 (jetting)
Burial depth (m) : 2
Product : Power Cable
Weight (kg/m) : max 19
Diameter : max 139 mm

Other projects

  • 2020 Dunant

    Pre lay shore end. 5 km cable installation with laying and burial. Installation of articulated pipes.
    Burial system : TO Mobile (jetting)
    Plus d’infos
  • 2017 BEATRICE OWF

    Provision of personnel and equipment to carry out the post lay burial of 56 infield power cables.
    Burial system : ROVJET 1210 (jetting)
    Plus d’infos
  • 2015 SEA LION Rostock

    1 shore end in Germany + Laying and burial of the same cable offshore in Denmark, in low water depths.
    Burial system : ROVJET404 + EBJ (jetting)
    Plus d’infos