Post-Lay burial of the export power cable of the Thornton Bank Offshore Windfarm.

Location : Thornton Bank Windfarm, Ostende (BELGIUM)
Client : VSMC / C-POWER

Product : Power Cable 
Length (km): 36
Water depth (m) : 0 to 26
Vessel : DP Vessel + Barge
Burial system : ROVJET605 + ROVJET806 (jetting)
Burial depth (m) : 1.5 
Weight (kg/m) : max 44
Diameter : max 234 mm