2013 LONDON ARRAY

Provision of personnel and equipment to carry out the post burial of 54 infield cables, some in very shallow water.

Location : LONDON ARRAY Offshore Windfarm / Thames Estuary (UK)
Client : VSMC

Product : Power Cable
Length (km): 55
Water depth (m) : 0 to 25
Vessel : Barge
Burial system : ROVJET605 (jetting)
Burial depth (m) : 1.5 
Weight (kg/m) : max 50
Diameter : max 157 mm