Home » Projets » 2014 BUTENDIEK

2014 BUTENDIEK

Provision of personnel and equipment to carry out the post burial of 86 infield power cables.

Location : BUTENDIEK Offshore Windfarm / German North Sea
Client : VBMS

Product : Power Cable 
Length (km): 81
Water depth (m) : up to 22 m
Vessel : DP Vessel
Burial system : ROVJET806 (jetting)
Burial depth (m) : 1
Weight (kg/m) : –
Diameter : 

Other projects

  • 2015 ABU ALI

    Provision of personnel and equipment to carry out the post lay trenching of a 15 kV power composite cable.
    Burial system : TM03 (trenching)
    Plus d’infos
  • 2018 ASC Perth

    1 separate shore end. 10 km cable installation with laying and burial.  Installation of articulated pipes.
    Burial system : TO Mobile (jetting)
    Plus d’infos
  • 2008 DELMA

    Post trenching of 2 power cables between Shuwaihat (mainland) and Delma Island. Installation of articulated pipes.
    Burial system : TM04 (Trencher)
    Plus d’infos