Home » Projets » 2020 Dunant

2020 Dunant

Pre lay shore end. 5 km cable installation with laying and burial. Installation of articulated pipes.

Location : Saint Hilaire de Riez / France
Client : Subcom

Product : Fibre optic cable 
Length (km): 5
Water depth (m) : up to 15 m
Vessel : DP Vessel
Burial system : TO Mobile NV (jetting)
Burial depth (m) :

Other projects

  • 2023 BLUE GENOA

    2 x Direct landings at Genoa in a directional borehole. Shell installation
    Burial system :
    Plus d’infos
  • 2023 2 AFRICA SOUTH AFRICA

    1 x Direct landing in Port Elizabeth, shell installation, post beaching, clamp installation. Installation of grounding system
    Burial system :
    Plus d’infos
  • 2005 SEA-ME-WE 4

    Direct shore ends / Laying and burial of FO cable
    Burial system : Dredge pump (with divers)
    Plus d’infos