Home » Projets » 2020 Dunant

2020 Dunant

Pre lay shore end. 5 km cable installation with laying and burial. Installation of articulated pipes.

Location : Saint Hilaire de Riez / France
Client : Subcom

Product : Fibre optic cable 
Length (km): 5
Water depth (m) : up to 15 m
Vessel : DP Vessel
Burial system : TO Mobile NV (jetting)
Burial depth (m) :

Other projects

  • 2011 ACE – SENEGAL

    2 direct FO shore-ends in Dakar (Senegal). Protection of cable (burial, articulated pipes, grout bags)
    Burial system : EBJ (Jetting)
    Plus d’infos
  • 2001 I 2 I / Shore end MADRAS

    Cable lay and burial – 8 km CHENNAI shore end.
    Burial system : TJV05 + TJV04 (Jetting) + ESV07 (Plough)
    Plus d’infos
  • 2022 2 AFRICA & BLUE

    Pre Lay Grapnel Run (PLGR) & Route Clearance (RC) for the BLUE and 2Africa projects in the Mediterranean Sea
    Burial system :
    Plus d’infos