Home » Projets » 2014 SAFANIYA 2

2014 SAFANIYA 2

Provision of personnel and equipment to carry out the trenching of a 115 kV power composite cable in shallow water.

Location : SAFANIYA 2 oild field – Saudi Arabia
Client : Mc Dermott / Saudi Aramco

Product : Power Composite Cable
Length (km): 7.4
Water depth (m) : 0 to 7.5
Vessel : Barge
Burial system : TM03 (trenching)
Burial depth (m) : 1
Weight (kg/m) : 52
Diameter : 214 mm

Other projects

  • 2024 HAI LONG

    Post Lay Burial of EXP
    Burial system :
    Plus d’infos
  • 2008 TAURT FIELD DEVELOPMENT

    Post trenching of subsea umbilical / PLIB
    Burial system : ROVJET401 (Jetting)
    Plus d’infos
  • 2022 2 AFRICA Spain

    1 x Direct landing in Barcelona, shell installation and post-burial. Installation of grounding system
    Burial system :
    Plus d’infos