Provision of personnel and equipment to carry out the trenching of a 115 kV power composite cable in shallow water.

Location : SAFANIYA 2 oild field – Saudi Arabia
Client : Mc Dermott / Saudi Aramco

Product : Power Composite Cable
Length (km): 7.4
Water depth (m) : 0 to 7.5
Vessel : Barge
Burial system : TM03 (trenching)
Burial depth (m) : 1
Weight (kg/m) : 52
Diameter : 214 mm

Other projects

  • 2015 BALTIC 2

    Provision of personnel and equipment to carry out the post burial of 75 infield power cables.
    Burial system : ROVJET806 (jetting)
    Plus d’infos
  • 2015 MANIFA

    Provision of personnel and equipment to carry out the trenching of 3 power cables and 2 fiber optic cables.
    Burial system : TM03 (trencher)
    Plus d’infos
  • 2015 AMRUMBANK

    Provision of personnel and equipment to carry out the post burial of 86 infield power cables.
    Burial system : ROVJET810 (jetting)