Provision of personnel and equipment to carry out the post burial of 75 infield power cables.

Location : BALTIC 2 Offshore Windfarm / German Baltic Sea
Client : Siem Offshore Contractors

Product : Power Cable 
Length (km): 61
Water depth (m) : up to 45 m
Vessel : DP Vessel
Burial system : ROVJET806 (jetting)
Burial depth (m) : 2
Weight (kg/m) : –
Diameter : 