2015 FITZROY Port Hedland

2 separate shore ends. Double 44km cable installation with simultaneous laying and trenching (both cables in the same trench) and surface lay with a minimum 5m separation between both cables. Installation of articulated pipes.

Location : Port Hedland / Australia
Client : Alcatel-Lucent Submarine Networks Ltd

Product : Fibre optic cable
Length (km): 2 x 44
Water depth (m) : up to 17 m
Vessel : Barge
Burial system : TM04 (trenching) + EBJ (jetting)
Burial depth (m) : 0.5
Weight (kg/m) : 3.5
Diameter : 35

Other projects

  • 2017 LTAII

    Provision of personnel and equipment to carry out trebsching services on a total of 10 submarine power cables.
    Burial system : TM03 + TM04 (trenchers)
    Plus d’infos
  • 2022 2/AFRICA GENES

    2 x Direct landings in Genoa. Installation of shells and post-sinking. Installation of grounding system
    Burial system :
    Plus d’infos
  • 2009 IMEWE/MENA/TEN/EIG

    FO cable shore ends, PLIB and installation of articulated pipes.
    Burial system : TO Mobile
    Plus d’infos