Home » Projets » 2015 SEA LION Rostock

2015 SEA LION Rostock

1 shore end in Germany :  laying and burial of FO cable + installation of articulated pipes. Laying and burial of the same cable offshore in Denmark, in low water depths.

Location : Germany – Denmark
Client : Alcatel-Lucent Submarine Networks Ltd

Product : Fibre optic cable
Length (km): 9.7 + 8.2
Water depth (m) : up to 15 m
Vessel : DP vessel
Burial system : ROVJET404 + EBJ (jetting)
Burial depth (m) : 1
Weight (kg/m) : 3.6
Diameter : 35

Other projects

  • 2020 TANNAT and MALBEC Systems

    Separate landing. Laying and burial of 2 fiber optic cables in Las Toninas (Argentina). Installation of shells.
    Burial system : ROVJET 404
    Plus d’infos
  • 2013 ANHOLT

    Post Lay Inspection and Burial of 111 infield power cables
    Burial system : ROVJET806 (jetting)
    Plus d’infos
  • 2015 ABU ALI

    Provision of personnel and equipment to carry out the post lay trenching of a 15 kV power composite cable.
    Burial system : TM03 (trenching)
    Plus d’infos