Provision of personnel and equipment to carry out the post lay burial of 18 infield power cables.

Location : Trianel Borkum II Offshore Windfarm / German waters
Client : Seaway Offshore Cables

Product : Power Cable 
Length (km): 27
Water depth (m) : up to 33 m
Vessel : DP Vessel
Burial system : ROVJET1210 (jetting)
Burial depth (m) : 1.7