Home » Projets » 2023 ZAKYNTIS

2023 ZAKYNTIS

LD Travocean was subcontracted by Asso Subsea for trenching work. ROVJET 1217 was deployed on the TSV MV Astrea to carry out PLB water jet cleaning on the 21 km electrical interconnection.

Location: Greece
Customer : ASSO SUBSEA

Length (km): 16.2 km
Water depth (m): maximum 515 m
Vessel: MV ASTREA
Beaming system: ROVJET 1217
Beaming depth (m): 2.1 m
Product : Power cable
cable type: 2 types of jointed cable:
ø22cm
ø21cm

Other projects

  • 1997 SOUTH KOREA

    Main land to Island / HVDC power cable extension with piggy-backed fibre optic cable
    Burial system : COPS (mattresses protection)
    Plus d’infos
  • 2011 WALNEY 1

    Post Lay Inspection and Burial of infield power cables
    Burial system : ROVJET605 (jetting)
    Plus d’infos
  • 2008 KASHAGAN

    Fibre optic cable laying and burial between Island D and Atyrau (Kazahkstan)
    Burial system : TM03 (Trencher) + ESV12 (Plough)
    Plus d’infos