Home » Projets » 2020 Dunant

2020 Dunant

Pre lay shore end. 5 km cable installation with laying and burial. Installation of articulated pipes.

Location : Saint Hilaire de Riez / France
Client : Subcom

Product : Fibre optic cable 
Length (km): 5
Water depth (m) : up to 15 m
Vessel : DP Vessel
Burial system : TO Mobile NV (jetting)
Burial depth (m) :

Other projects

  • 2011 WACS

    FO cable separate and direct shore ends in Congo and Angola / PLIB / installation of mattresses with ROS
    Burial system : TJV05 – EBJ (jetting) – ROS (mattresses)
    Plus d’infos
  • 1999 ELGIN FRANKLIN

    Platform to platform / Composite power and communication cable + 1 composite power / communication cable + 1 umbilical.
    Burial system : CASTOR 2 (Trencher)
    Plus d’infos
  • 2024 MARSEILLE

    1 x Direct landing in Marseille, installation of shells, post-sinking, installation of posidonia anchors. Installation of grounding system
    Burial system :