2020 TANNAT and MALBEC Systems
Pre Lay Grapnel Run and Route Clearance to a depth of 1,500 m in May.
Separate landing. Laying and burial of 2 fiber optic cables in Las Toninas (Argentina).
Installation of shells.
Location: Las Toninas (Argentina)
Client: Alcatel Submarine Networks (ASN)
Product: Optical fiber
Length: 2 x 7 km
Depth: 15 m
Ship: DP
Burial system: ROVJET 404
Burial depth: 1.5 m
Period: November