Home » Projets » 2022 2/AFRICA GENES

2022 2/AFRICA GENES

2 x Direct landings in Genoa. Installation of shells and post-sinking. Installation of grounding system

Location: Genes ITALY
Customer : ALCATEL SUBMARINE NETWORKS

Length (km): 2 x 700 m
Water depth (m) :
Vessel: N/A
Beam system: EBJ
Beam depth (m): 2.0 m
Product : Fiber Optic Cable
cable type: ø44mm

Other projects

  • 2016 MARJAN GOSP

    Provision of personnel and equipment to carry out the post-lay burial of one 115 kV power cable.
    Burial system : TM03 (trenching)
    Plus d’infos
  • 2025 2 AFRICA PEARLS

    Separate landing at Al Khobar. Laying and post-wiring of 35 km of fiber optic cable
    Burial system :
    Plus d’infos
  • 2011 WALNEY 1

    Post Lay Inspection and Burial of infield power cables
    Burial system : ROVJET605 (jetting)
    Plus d’infos