Provision of personnel and equipment to carry out the post burial of 86 infield power cables.

Location : BUTENDIEK Offshore Windfarm / German North Sea
Client : VBMS

Product : Power Cable 
Length (km): 81
Water depth (m) : up to 22 m
Vessel : DP Vessel
Burial system : ROVJET806 (jetting)
Burial depth (m) : 1
Weight (kg/m) : –
Diameter : 