2016 VEJA MATE

Provision of personnel and equipment to carry out the post lay burial of 73 infield power cables.

Location : Veja Mate Windfarm / North sea (German waters)
Client : Siem Offshore Contractors

Product : Power Cable 
Length (km): 87
Water depth (m) : up to 40 m
Vessel : DP Vessel
Burial system : ROVJET810 (jetting)
Burial depth (m) : 1.5