Home » Projets » 2000 PEC / LEVEL 3/ FLUTE

2000 PEC / LEVEL 3/ FLUTE

PLIB works on telecom fibre optic cable crossings.

Location : ENGLISH CHANNEL (Manche)
Client : ALCATEL SUBMARINE NETWORKS

Length (km): 13,8
Water depth (m) : 56
Vessel : DP Vessel
Burial system : MED 1: Dredge pump / jetting tool
Burial depth (m) : 0,8-1,2
Product : Fibre optic cable
Weight (kg/m) : 5
Diameter : 41 mm

Other projects

  • 2023 ZAKYNTIS

    LD Travocean was subcontracted by Asso Subsea for trenching work. ROVJET 1217 was deployed on the TSV MV Astrea to carry out PLB water jet cleaning on the 21 km electrical interconnection.
    Burial system :
    Plus d’infos
  • 2001 SAT 3

    DOUALA and LIBREVILLE shore ends / Laying and burial of FO cable
    Burial system : TJV05 – TJV04 (Jetting) + ESV12 (Plough)
    Plus d’infos
  • 2012 CAT – THAÏLAND

    2 separate pre-laid shore ends at Sri Racha and Songkhla + Installation of articulated pipes.
    Burial system : EBJ 04 + ESV12 (jetting)
    Plus d’infos