PLIB works on telecom fibre optic cable crossings.

Location : ENGLISH CHANNEL (Manche)
Client : ALCATEL SUBMARINE NETWORKS

Length (km): 13,8
Water depth (m) : 56
Vessel : DP Vessel
Burial system : MED 1: Dredge pump / jetting tool
Burial depth (m) : 0,8-1,2
Product : Fibre optic cable
Weight (kg/m) : 5
Diameter : 41 mm