2000 PEC / LEVEL 3/ FLUTE

PLIB works on telecom fibre optic cable crossings.

Location : ENGLISH CHANNEL (Manche)
Client : ALCATEL SUBMARINE NETWORKS

Length (km): 13,8
Water depth (m) : 56
Vessel : DP Vessel
Burial system : MED 1: Dredge pump / jetting tool
Burial depth (m) : 0,8-1,2
Product : Fibre optic cable
Weight (kg/m) : 5
Diameter : 41 mm

Other projects

  • 2016 VEJA MATE

    Provision of personnel and equipment to carry out the post lay burial of 73 infield power cables.
    Burial system : ROVJET 810 (jetting)
    Plus d’infos
  • 2021 YUNLIN OWF

    Provision of personnel and equipment to carry out the post lay burial of infield array cables.
    Burial system :
    Plus d’infos
  • 2012 CAT – THAÏLAND

    2 separate pre-laid shore ends at Sri Racha and Songkhla + Installation of articulated pipes.
    Burial system : EBJ 04 + ESV12 (jetting)
    Plus d’infos