Home » Projets » 2003 ILE D’YEU

2003 ILE D’YEU

Mainland to island / Shore ends / Laying and burial of 20 kV pc

Location : FRANCE – ILE D’YEU/SAINT JEAN DE MONTS
Client : NEXANS

Length (km): 18
Water depth (m) : 8
Vessel : Barge
Burial system : N.A.
Burial depth (m) : 1,8
Product : Power Cable
Weight (kg/m) : 28
Diameter : 111 mm

Other projects

  • 2017 IFA 2000 CABLES REPAIR

    Repair of 4 power cables being part of the IFA 2000 link .
    Burial system : MED 1 (Dredge pump) + ROVJET806 (jetting)
    Plus d’infos
  • 2014 PERENCO RDC CONGO

    Laying of 43 km of power cable between mainland / platforms and platforms.
    Burial system : ROVJET806 + EBJ (jetting)
    Plus d’infos
  • 2015 MANIFA

    Provision of personnel and equipment to carry out the trenching of 3 power cables and 2 fiber optic cables.
    Burial system : TM03 (trencher)
    Plus d’infos