2005 PERENCO Gabon

The purpose of this operation was to surface lay 70 kM of power cable in Peranco Gabon Fields, in water depth less than 35m.

Location : GABON (South of PORT-GENTIL)
Client : PERENCO France

Longueur (km): 72
Water depth (m) : 30
Vessel : DP Vessel
Burial system : N.A.
Burial depth (m) : N.A.
Product : Power Cable
Weight (kg/m) : 19
Diameter : 112 / 108 / 96 mm

Other projects

  • 2014 GÉOCEAN BÉNIN

    Laying of 14km of power cable between mainland and a platform. Burial in shallow water from 8m to the beach.
    Burial system : EBJ (jetting)
    Plus d’infos
  • 2008 PERENCO RDC

    Cable laying and burial between mainland and platforms. Barge operating for pipe laying + special liftings + J-tube pullin.
    Burial system : EBJ 04 (jetting)
    Plus d’infos
  • 2007 PICOT / GONDWANA

    FO cable shore ends – Post lay burial
    Burial system : EBJ 04 (jetting)