Home » Projets » 2009 KASHAGAN

2009 KASHAGAN

Provison of burial services for 1 power cable and 2 umbilicals.

Location : Kashagan oil field – Kazakhstan
Client : SONSUB (for SAIPEM)

Length (km): 18
Water depth (m) : 6
Vessel : Barge
Burial system : TM03 (Trencher)
Burial depth (m) : 2
Product : Flowline / Power cable
Weight (kg/m) : 1,4 
Diameter : 23 mm

Other projects

  • 1999 ELGIN FRANKLIN

    Platform to platform / Composite power and communication cable + 1 composite power / communication cable + 1 umbilical.
    Burial system : CASTOR 2 (Trencher)
    Plus d’infos
  • 2008 PERENCO RDC

    Cable laying and burial between mainland and platforms. Barge operating for pipe laying + special liftings + J-tube pullin.
    Burial system : EBJ 04 (jetting)
    Plus d’infos
  • 1999 CIRCE

    Cable deburial / reburial and cable loop burial on CIRCE fibre optic cable system.
    Burial system : MED1 (Dredge pump) – CASTOR (Trencher)
    Plus d’infos